Thomson Line (TSL)
With about 30-km long stretch that will connect commuters living along the North South Corridor directly to the heart of the city and developments in the Marina Bay Area. TSL will run from Woodlands in the North to Marina Bay. Fully underground, TSL will have 22 stations, including six interchange stations. These interchange stations will link the East West Line (EWL), North South Line (NSL), North EAST Line (NEL), Circle Line (CCL) and future Downtown Line (DTL), for greater accessibility and improve travel time.
Clients
Sato Kogyo (S) Pte Ltd – Contract T212 Construction of Upper Thomson Station and Tunnels for Thomson Line
Scope of Works:
- Recharge and Relief wells
- Micro Pile
- Rock Blasting using Explosives with Electronic Detonators
- Cross Passage
Project Start/End: April 2015 – Current
Sinohydro Corporation Limited – Contract T217 Construction of Napier Station and Tunnels for Thomson Line
Scope of Works:
- Rock blasting using explosives using electronic detonators
- Nonex chemical breaking
- Shotcreting for Tunnel eye
- Ground support works
Project Start/End: Oct 2015 – Current
Woh Hup (Private) Ltd – T205 Construction of Woodlands South Station for Thomson Line
Scope of Works:
- Recharge Well Works
Project Start/End: Dec 2014 – Current
Hock Lian Seng Infrastructure Pte Ltd – Contract T223 Construction of Maxwell Station
Scope of Works:
- Recharge Well Works
Project Start/End: Nov 2014 – Current